[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106803":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106803,782,1,"单选题","关于进度偏差和投资偏差，下列说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","进度偏差为正值时，表示进度提前",false,{"key":16,"text":17,"correct":14},"B","进度偏差为负值时，表示进度拖延",{"key":19,"text":20,"correct":21},"C","投资偏差为正值时，表示投资增加",true,{"key":23,"text":24,"correct":14},"D","投资偏差为正值时，表示投资节约","投资偏差指投资的实际值与计划值的差值，投资偏差为正表示投资超支，结果为负表示投资节约。进度偏差结果为正值，表示工期拖后；进度偏差结果为负值，表示工期提前。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]