[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106793":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106793,782,1,"单选题","对于违约责任的处理，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","因承包人违约造成施工合同解除后，发包人应立即承包人应得到但未支付的工程价款和费用",false,{"key":16,"text":17,"correct":18},"B","因承包人违约造成施工合同解除的，监理人应就合同解除前承包人应得到但未支付的工程价款和费用签发付款证书，但应扣除根据施工合同约定应由承包人承担的违约费用",true,{"key":20,"text":21,"correct":14},"C","发包人违约承包人按合同的约定暂停施工14天后，发包人仍不纠正违约行为的，承包人可向发包人发出解除合同通知",{"key":23,"text":24,"correct":14},"D","发包人应在解除合同后56天内向承包人支付相关金额","A项，因承包人违约造成施工合同解除后，发包人应暂停对承包人的一切付款，查清各项付款和已扣款金额，包括承包人应支付的违约金。C项，发包人违约承包人按合同的约定暂停施工28天后，发包人仍不纠正违约行为的，承包人可向发包人发出解除合同通知。D项，根据《水利水电工程标准文件》通用合同条款规定，发包人应在解除合同后28天内向承包人支付相关金额。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]