[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106785":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106785,782,1,"单选题","工程变更引起措施项目发生变化的，承包人提出调整措施项目费的，应事先将拟实施的方案提交发包人确认。拟实施的方案经发承包双方确认后执行，并应按规定调整措施项目费。其中，（ ）应按照实际发生变化的措施项目调整，不得浮动。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","夜间施工增加费",false,{"key":16,"text":17,"correct":14},"B","脚手架工程费",{"key":19,"text":20,"correct":14},"C","二次搬运费",{"key":22,"text":23,"correct":24},"D","安全文明施工费",true,"措施项目费调整规则为：①安全文明施工费，按照实际发生变化的措施项目调整，不得浮动。②采用单价计算的措施项目费，按照实际发生变化的措施项目按分部分项工程费的调整方法确定单价。③按总价（或系数）计算的措施项目费，除安全文明施工费外，按照实际发生变化的措施项目调整；但应考虑承包人报价浮动因素，即调整金额按照规定计算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]