[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106784":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106784,782,1,"单选题","在具备施工条件的前提下，发包人应在双方签订合同后的一个月内或约定的开工日期前（ ）天内预付工程款。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","14",{"key":23,"text":24,"correct":18},"D","28","在具备施工条件的前提下，发包人应在双方签订合同后的一个月内或约定的开工日期前的7天内预付工程款。若发包人未按合同约定预付工程款，承包人应在预付时间到期后10天内向发包人发出要求预付的通知。发包人收到通知后仍不按要求预付，承包人可在发出通知14天后停止施工。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]