[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106781":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106781,782,1,"单选题","下列各项中，按施工图纸所示计算的有效重量以t或kg为单位计量的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","帷幕灌浆",true,{"key":16,"text":17,"correct":18},"B","劈裂灌浆",false,{"key":20,"text":21,"correct":18},"C","回填灌浆",{"key":23,"text":24,"correct":18},"D","接缝灌浆","A项，帷幕灌浆、固结灌浆的灌浆按设计净干灰耗量计算有效干灰重量以t为单位计量。BCD三项，劈裂灌浆、回填灌浆、接缝灌浆和接触灌浆按施工图纸所示灌浆区域计算的有效灌浆面积以m2为单位计量。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]