[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106780":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106780,782,1,"单选题","下列各项费用中，除合同另有约定外，发包人不另行支付的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","现场试验室的建设费用",false,{"key":16,"text":17,"correct":14},"B","场内施工道路的建设所需的费用",{"key":19,"text":20,"correct":21},"C","承包人承担的超大、超重件的运输费用",true,{"key":23,"text":24,"correct":14},"D","施工用电设施的建设、移设和拆除工作所需费用","A项，承包人现场试验室的建设费用，由发包人按《工程量清单》所列相应项目的总价支付。B项，承包人根据合同要求完成场内施工道路的建设和施工期的管理维护工作所需的费用，由发包人按《工程量清单》相应项目的工程单价或总价支付。C项，承包人承担的超大、超重件的运输费用，均由承包人自行负责，发包人不另行支付。D项，承包人根据合同要求完成施工用电设施的建设、移设和拆除工作所需的费用，由发包人按《工程量清单》相应项目的工程单价或总价支付。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]