[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106778":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106778,782,1,"单选题","工程计量的项目不包括（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程量清单中的项目",false,{"key":16,"text":17,"correct":14},"B","已由监理人发出变更指令的工程变更项目",{"key":19,"text":20,"correct":21},"C","承包人自己规划设计的项目",true,{"key":23,"text":24,"correct":14},"D","合同文件中规定应由监理人现场确认的，并已获得监理人批准同意的项目","在工程计量中，只计量合同中规定的项目。对合同工程量清单规定以外的项目（如承包人自己规划设计的施工便道、临时栈桥、脚手架，以及为施工需要而修建的施工排水泵、河岸护堤、隧洞内避车洞、临时支护等）将不予计量。因此，应计量的项目只包括：①工程量清单中的全部项目。②已由监理人发出变更指令的工程变更项目。③合同文件中规定应由监理人现场确认的，并已获得监理人批准同意的项目。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]