[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106777":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106777,782,1,"单选题","下列合同形式中，适用于工程量变化不大的项目的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","固定总价合同",false,{"key":16,"text":17,"correct":14},"B","可调值总价合同",{"key":19,"text":20,"correct":21},"C","固定工程量总价合同",true,{"key":23,"text":24,"correct":14},"D","纯单价合同","固定工程量总价合同，即发包人要求投标者在投标时按单价合同办法分别填报分项工程单价，从而计算出工程总价，据之签订合同。原定工程项目全部完成后，根据合同总价付款给承包人。如果改变设计或增加类似项目，则用合同中已确定的单价来计算新的工程量和调整总价，这种方式适用于工程量变化不大的项目。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]