[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106775":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106775,782,1,"单选题","在总价合同实施中，由于通货膨胀而使工料成本增加，按合同规定可以对合同总价进行相应的调整的合同形式称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","固定总价合同",false,{"key":16,"text":17,"correct":18},"B","可调值总价合同",true,{"key":20,"text":21,"correct":14},"C","包干合同",{"key":23,"text":24,"correct":14},"D","固定工程量总价合同","在总价合同实施中，由于通货膨胀而使工料成本增加，按合同规定可以对合同总价进行相应的调整的合同形式称为可调值总价合同。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]