[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106765":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106765,782,1,"单选题","下列关于材料预算价格的相关说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","是指材料的出厂价格",false,{"key":16,"text":17,"correct":14},"B","包括工地分仓库到各施工点的运杂费",{"key":19,"text":20,"correct":21},"C","包括材料原价、运杂费、运输保险费和采购及保管费",true,{"key":23,"text":24,"correct":14},"D","是指材料从供应地运到工地分仓库（或堆放场地）的价格","材料预算价格是指材料从供应地运到工地分仓库（或堆放场地）的出库价格。材料预算价格一般包括材料原价、运杂费、运输保险费、采购及保管费4项。从工地的材料总库运到分仓库所发生的场内运杂费应计入材料预算价格；而从工地分仓库到各施工点的运杂费用已计入定额内，在材料预算价格中不予计算。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]