[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106763":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106763,782,1,"单选题","设计单位应根据国家批准的设计概算静态总投资，作为建设项目设计的最高限额。若因设计单位责任，增加了工程静态投资4%以上时，应根据超过相应概算静态投资的大小实行惩罚。超过限额（ ）者，扣相应比例2倍的设计费。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10%以内",false,{"key":16,"text":17,"correct":14},"B","10%～20%",{"key":19,"text":20,"correct":21},"C","20%以上",true,{"key":23,"text":24,"correct":14},"D","30%以上","如由于设计单位的责任，增加了工程静态投资4%以上时，应根据超过相应概算静态投资的大小实行惩罚：①超过限额10%以内者，扣相应比例的设计费，如超过限额5%，扣设计费5%；②超过限额10%～20%者，扣相应比例1.5倍的设计费；③超过限额20%以上者，扣相应比例2倍的设计费；④超过限额30%以上者，如无特殊原因，建议设计证书批准部门降低设计单位的设计等级。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]