[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106734":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106734,782,1,"单选题","某建设项目，第1～3年每年年末投入建设资金400万元，第4～8年每年年末获得利润700万元，则该项目的静态投资回收期为（ ）年。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":18},"B","4.71",true,{"key":20,"text":21,"correct":14},"C","5",{"key":23,"text":24,"correct":14},"D","5.71","项目建成投产后各年的净收益（净现金流量）均相同时，静态投资回收期的计算公式为： 故本题中项目的静态投资回收期为：400×3÷700＋3＝4.71（年）。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]