[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106726":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106726,782,1,"单选题","在技术设计阶段，影响项目投资的可能性为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10%～35%",false,{"key":16,"text":17,"correct":18},"B","35%～75%",true,{"key":20,"text":21,"correct":14},"C","75%～90%",{"key":23,"text":24,"correct":14},"D","90%～95%","在前期工作阶段，影响项目投资的可能性为90%～95%；在初步设计阶段，影响项目投资的可能性为75%～90%；在技术设计阶段，影响项目投资的可能性为35%～75%；在施工图设计阶段，影响项目投资的可能性则为10%～35%；在施工阶段，影响项目投资的可能性约为10%。很显然，项目投资控制的重点在于施工以前的投资决策和设计阶段，而在项目作出投资决策后，控制项目投资的关键就在于设计。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]