[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106720,782,1,"单选题","建设工程投资的静态投资部分不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","基本预备费",false,{"key":16,"text":17,"correct":18},"B","建设期融资利息",true,{"key":20,"text":21,"correct":14},"C","设备工器具购置费",{"key":23,"text":24,"correct":14},"D","建筑安装工程费","静态投资部分不包括建设期融资利息和涨价预备费。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]