[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106718":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106718,782,1,"单选题","《水利工程设计概（估）算编制规定》(水总[2014]429 号)，联合试运转费属于（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","独立费用",true,{"key":16,"text":17,"correct":18},"B","安装工程费",false,{"key":20,"text":21,"correct":18},"C","生产准备费",{"key":23,"text":24,"correct":18},"D","设备费","联合试运转费属于独立费用。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]