[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106707":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106707,782,1,"单选题","严格审查初步设计、技术设计、施工图设计、施工组织设计属于项目投资控制措施中的（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","组织措施",false,{"key":16,"text":17,"correct":18},"B","技术措施",true,{"key":20,"text":21,"correct":14},"C","经济措施",{"key":23,"text":24,"correct":14},"D","合同措施","项目投资的控制措施包括组织措施、技术措施、经济措施和合同措施。其中，技术措施包括：①重视设计多方案选择；新版章节练习，考前压卷，金考典软件考前更新，下载链接 www.jinkaodian.com②严格审查初步设计、技术设计、施工图设计、施工组织设计；③深入技术领域研究节约投资的可能性。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]