[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106687":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106687,782,1,"单选题","全面质量管理的基本方法概括为四个阶段八个步骤，其中包括八个步骤中的前四个步骤的阶段是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","实施阶段",false,{"key":16,"text":17,"correct":14},"B","检查阶段",{"key":19,"text":20,"correct":21},"C","计划阶段",true,{"key":23,"text":24,"correct":14},"D","处理阶段","本题考查的是质量控制基本概念。计划阶段包括八个步骤中的前四个步骤：查找问题；进行排列；分析问题产生的原因；制定对策和措施",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]