[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106673":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106673,782,1,"单选题","质量控制中的 PDCA 循环是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","计划—实施—对比—处理",false,{"key":16,"text":17,"correct":14},"B","计划—实施—检查—纠偏",{"key":19,"text":20,"correct":14},"C","计划—实施—对比—纠偏",{"key":22,"text":23,"correct":24},"D","计划—实施—检查—处理",true,"PDCA 循环，又称“戴明环”。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]