[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106642":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106642,782,1,"单选题","在危险源评价的方法中，作业条件—管理因子危险性评价法适用于（ ）评价。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","决策期",false,{"key":16,"text":17,"correct":14},"B","设计期",{"key":19,"text":20,"correct":14},"C","施工期",{"key":22,"text":23,"correct":24},"D","各阶段",true,"本题考查的是施工危险源风险评价及重大危险源控制。作业条件—管理因子危险性评价法适用于各阶段评价。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]