[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106628":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106628,782,1,"单选题","事故或危险性事件发生的可能性L值为6，表示（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","完全可以预料",false,{"key":16,"text":17,"correct":14},"B","可能，但不经常",{"key":19,"text":20,"correct":21},"C","相当可能",true,{"key":23,"text":24,"correct":14},"D","可能性小，完全意外","事故或危险性事件发生的可能性L值与作业类型有关，参照《水利水电工程施工危险源辨识与风险评价导则（试行）》（办监督函[2018]1693号），L值按表9-2-1确定。由表可知，L值为6表示相当可能。 表9-2-1 事故发生的可能性L值对照表",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]