[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106625,782,1,"单选题","关于施工危险源辨识方法选择的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","危险源辨识应必须采用直接判定法",true,{"key":16,"text":17,"correct":18},"B","安全检查表和因果分析图的适用范围广、简便，易于掌握和建设工程的标准、规范相一致，容易为现场管理人员和操作人员接受",false,{"key":20,"text":21,"correct":18},"C","预先危险性分析适合用于对新材料、新结构、新工艺存在的危险性进行预先分析",{"key":23,"text":24,"correct":18},"D","事件树分析和事故树分析可以进行定量分析，适用于大型施工企业对复杂的施工项目进行危险源辨识","危险源辨识应先采用直接判定法，不能用直接判定法辨识的，可采用其他方法进行判定。当本工程区域内出现符合《水利水电工程施工危险源辨识与风险评价导则（试行）》（办监督函[2018]1693号）（附件2）中《水利水电工程施工重大危险源清单》的任何一条要素的，可直接判定为重大危险源。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]