[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106619":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106619,782,1,"单选题","关于爆破施工安全控制措施的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","严格炮工持证上岗制度",false,{"key":16,"text":17,"correct":14},"B","正确设计爆破施工方案，明确安全技术措施",{"key":19,"text":20,"correct":21},"C","装药后，严格检查炮眼深度、方位、距离是否符合设计方案",true,{"key":23,"text":24,"correct":14},"D","坚持爆破效果分析制度","爆破施工安全控制措施：①充分掌握爆破施工现场周围环境，明确保护范围和重点保护对象。②正确设计爆破施工方案，明确安全技术措施。③严格炮工持证上岗制度，并努力提高他们的安全意识，要求按章作业。④装药前，严格检查炮眼深度、方位、距离是否符合设计方案。⑤装药后检查孔眼预留堵塞长度是否符合要求，检查覆盖网是否连接牢固。⑥坚持爆破效果分析制度，通过检查分析来总结经验和教训，制定改进措施和预防措施。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]