[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106602":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106602,782,1,"单选题","监理单位在审核施工单位报送的度汛方案时，应重点审核的内容不包括（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","水文、气象及预报获取途径",false,{"key":16,"text":17,"correct":14},"B","工程巡查与监测方案",{"key":19,"text":20,"correct":14},"C","度汛保障",{"key":22,"text":23,"correct":24},"D","施工单位的资质情况",true,"监理单位在审核施工单位报送的度汛方案时，应重点审核以下几个方面：①度汛组织机构组成及职责、成员及分工。②汛期值班和检查制度，防汛人员值班计划、联系方式。③水文、气象及预报获取途径。④工程度汛标准。⑤汛前工程应达到的形象面貌。⑥度汛抢险防护措施，包括临时和永久工程建筑物的汛期抢险防护措施、施工区和生活区的度汛抢险防护措施等。⑦度汛保障，包括度汛抢险队伍保障、度汛物资和机械设备保障、通信保障、供电和交通保障、医疗和资金保障、宣传和培训等。⑧度汛涉及其他相关单位的联系人、联系方式等。⑨工程巡查与监测方案。⑩险情抢护措施及人员设备撤离方案。遭遇超标准洪水时的应急处置措施。后期处置等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]