[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106601":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106601,782,1,"单选题","不属于专项施工方案内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","资金计划",true,{"key":16,"text":17,"correct":18},"B","施工计划",false,{"key":20,"text":21,"correct":18},"C","劳动力计划",{"key":23,"text":24,"correct":18},"D","施工安全保证措施","专项施工方案应包括以下内容：①工程概况。危险性较大的专项工程概况、施工平面布置、施工要求和技术保证条件等。②编制依据。相关法律、法规、规范性文件、标准、规范及图纸（国标图集）、施工组织设计等。③施工计划。包括施工进度计划、材料与设备计划等。④施工工艺技术。技术参数、工艺流程、施工方法、质量标准、检查验收等。⑤施工安全保证措施。组织保障、技术措施、应急预案、监测监控等。⑥劳动力计划。专职安全生产管理人员、特种作业人员等。⑦设计计算书及相关图纸等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]