[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106537":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106537,782,1,"单选题","下列可能导致工程质量事故的因素中，属于违背基本建设程序的是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","未按有关施工规范施工",false,{"key":16,"text":17,"correct":14},"B","计算简图与实际受力情况不符",{"key":19,"text":20,"correct":14},"C","图纸技术交底不清",{"key":22,"text":23,"correct":24},"D","设计依据资料不可靠",true,"本题考查的是工程质量事故的成因。违背基本建设程序包括：可行性研究不充分。依据资料不充分或不可靠，或根本不做可行性研究；违章承接建设项目。如越级设计工程和施工，由于技术素质差，管理水平达不到标准要求。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]