[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106536":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106536,782,1,"单选题","下列不属于事故处理结论内容的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","事故已排除，可以继续施工",false,{"key":16,"text":17,"correct":18},"B","经修补处理后，部分满足使用要求",true,{"key":20,"text":21,"correct":14},"C","隐患已经消除，结构安全可靠",{"key":23,"text":24,"correct":14},"D","对耐久性影响的结论","事故处理结论的内容有以下几种：①事故已排除，可以继续施工。②隐患已经消除，结构安全可靠。③经修补处理后，完全满足使用要求。④基本满足使用要求，但附有限制条件如限制使用荷载，限制使用条件等。⑤对耐久性影响的结论。⑥对建筑外观影响的结论。⑦对事故责任的结论等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]