[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106516":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106516,782,1,"单选题","在施工过程中进行质量检验时，需要抽样检查的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","对下道工序影响大的中间产品",false,{"key":16,"text":17,"correct":14},"B","质量十分不稳定的工序",{"key":19,"text":20,"correct":14},"C","质量水平要求高的检验",{"key":22,"text":23,"correct":24},"D","具有破坏性的检验",true,"本题考查的是工程质量检验概述。ABC错误，属于必须全数检验的项目。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]