[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106496":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106496,782,1,"单选题","项目法人应当自工程开工之日起（ ）个工作日内，制定法人验收工作计划，报法人验收监督管理机关和竣工验收主持单位备案。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30",false,{"key":16,"text":17,"correct":14},"B","45",{"key":19,"text":20,"correct":21},"C","60",true,{"key":23,"text":24,"correct":14},"D","75","本题考查的是工程验收。项目法人应当自工程开工之日起60个工作日内，制定法人验收工作计划，报法人验收监督管理机关和竣工验收主持单位备案。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]