[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106495":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106495,782,1,"单选题","全面考核该阶段工程是否符合批准的设计文件要求，以确定工程能否继续进入到下一阶段施工或投入运行指的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程评定",false,{"key":16,"text":17,"correct":18},"B","工程验收",true,{"key":20,"text":21,"correct":14},"C","工程竣工",{"key":23,"text":24,"correct":14},"D","工程检验","本题考查的是工程验收。工程验收是工程建设进人到某一阶段的程序，借以全面考核该阶段工程是否符合批准的设计文件要求，以确定工程能否继续进入到下一阶段施工或投入运行，并履行相关的签证和交接验收手续。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]