[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106493":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106493,782,1,"单选题","项目法人应在（ ）60个工作日内，制定法人验收工作计划，报法人验收监督管理机关和竣工验收主持单位备案。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","可行性研究报告批准后",false,{"key":16,"text":17,"correct":14},"B","开工报告批准后",{"key":19,"text":20,"correct":14},"C","初步设备批准后",{"key":22,"text":23,"correct":24},"D","开工后",true,"本题考查的是工程验收。项目法人应在开工之日起60个工作日内，制定法人验收工作计划，报法人验收监督管理机关和竣工验收主持单位备案。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]