[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106491":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106491,782,1,"单选题","以下选项中，属于项目法人完成工程建设任务凭据的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","竣工证书",false,{"key":16,"text":17,"correct":18},"B","工程验收鉴定书",true,{"key":20,"text":21,"correct":14},"C","工程完工证书",{"key":23,"text":24,"correct":14},"D","保修责任终止证书","本题考查的是工程验收。竣工验收鉴定书是项目法人完成工程建设任务的凭据。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]