[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106489":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106489,782,1,"单选题","缺陷责任期满后（ ）个工作日内，发包人应向承包人颁发工程质量缺陷责任终止证书，并退还剩余的质量保证金。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","10",false,{"key":16,"text":17,"correct":14},"B","20",{"key":19,"text":20,"correct":21},"C","30",true,{"key":23,"text":24,"correct":14},"D","60","缺陷责任期满后30个工作日内，发包人应向承包人颁发工程质量缺陷责任终止证书，并退还剩余的质量保证金，但缺陷责任范围内的质量缺陷未处理完成的应除外。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]