[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106487":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106487,782,1,"单选题","项目法人组织单位工程验收时，应提前通知（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工单位",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":21},"C","质量和安全监督机构",true,{"key":23,"text":24,"correct":14},"D","法人验收监督管理机关","单位工程完工并具备验收条件时，施工单位应向项目法人提出验收申请报告。项目法人应在收到验收申请报告之日起10个工作日内决定是否同意进行验收。项目法人组织单位工程验收时，应提前通知质量和安全监督机构。新版章节练习，考前压卷，金考典软件考前更新，下载链接 www.jinkaodian.com主要建筑物单位工程验收应通知法人验收监督管理机关。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]