[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106473":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106473,782,1,"单选题","主要金属结构安装项目开工前，（ ）必须编制安装方案供监理工程师审查。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","承包单位",false,{"key":16,"text":17,"correct":14},"B","分包单位",{"key":19,"text":20,"correct":14},"C","供货单位",{"key":22,"text":23,"correct":24},"D","安装单位",true,"本题考查的是机电及金属结构设备安装质量控制。主要金属结构安装项目开工前，安装单位必须编制安装方案供监理工程师审查。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]