[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106467":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106467,782,1,"单选题","对于发包人提供的材料和工程设备，发包人应在材料和工程设备到货（ ）天前通知承包人。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","10",false,{"key":20,"text":21,"correct":18},"C","15",{"key":23,"text":24,"correct":18},"D","20","本题考查的是施工实施阶段影响因素的质量控制。发包人应在材料和工程设备到货7天前通知承包人，承包人会同监理机构在约定的时间内，赴交货地点共同进行验收。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]