[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106465":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106465,782,1,"单选题","（ ）在工程开工前应向承包人提供已有的与本工程有关的水文和地质勘测资料以及应由发包人提供的图纸。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","勘察单位",false,{"key":16,"text":17,"correct":14},"B","设计单位",{"key":19,"text":20,"correct":14},"C","监理人",{"key":22,"text":23,"correct":24},"D","发包人",true,"本题考查的是施工准备阶段影响因素的质量控制。发包人在工程开工前应向承包人提供已有的与本工程有关的水文和地质勘测资料以及应由发包人提供的图纸",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]