[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106456":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106456,782,1,"单选题","金属结构设备埋件的二期混凝土强度，达到（ ）以后方可拆模，拆模后应对埋件进行复测，并做好记录。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","70%",true,{"key":16,"text":17,"correct":18},"B","80%",false,{"key":20,"text":21,"correct":18},"C","90%",{"key":23,"text":24,"correct":18},"D","100%","本题考查的是机电及金属结构设备安装质量控制。埋件的二期混凝土强度达到70%以后方可拆模，拆模后应对埋件进行复测，并做好记录",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]