[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106447":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106447,782,1,"单选题","承包人按批准的技术方案组织施工，实施期间如需变更，则（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","重新报批",true,{"key":16,"text":17,"correct":18},"B","内部审核",false,{"key":20,"text":21,"correct":18},"C","专家论证",{"key":23,"text":24,"correct":18},"D","平行检验","本题考查的是施工准备阶段影响因素的质量控制。承包人按批准的技术方案组织施工，实施期间如需变更，需重新报批。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]