[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106445":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106445,782,1,"单选题","承包人更换项目经理应事先征得发包人同意，并应在更换（ ）天前通知发包人和监理机构。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","5",false,{"key":16,"text":17,"correct":18},"B","14",true,{"key":20,"text":21,"correct":14},"C","28",{"key":23,"text":24,"correct":14},"D","30","本题考查的是施工准备阶段影响因素的质量控制。承包人更换项目经理应事先征得发包人同意，并应在更换14天前通知发包人和监理机构",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]