[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106443":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106443,782,1,"单选题","合同项目开工条件的审查内容，包括（ ）两方面的准备工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","发包人和承包人",true,{"key":16,"text":17,"correct":18},"B","承包人和分包人",false,{"key":20,"text":21,"correct":18},"C","承包人和供货商",{"key":23,"text":24,"correct":18},"D","承包人和设计单位","本题考查的是施工准备阶段影响因素的质量控制。合同项目开工条件的审查内容，包括发包人和承包人两方面的准备工作",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]