[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106441":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1106441,782,1,"单选题","跟踪检测和平行检测工作都应由（ ）承担。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人",false,{"key":16,"text":17,"correct":14},"B","监理人",{"key":19,"text":20,"correct":14},"C","承包人",{"key":22,"text":23,"correct":24},"D","检测机构",true,"本题考查的是施工阶段质量控制概述。跟踪检测和平行检测工作都应由具有国家规定的资质条件的检测机构承担。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]