[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106433":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106433,782,1,"单选题","以下关于混凝土浇筑振捣的技术要求，说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","混凝土浇筑应以振捣代替平仓",true,{"key":16,"text":17,"correct":18},"B","振捣完应慢慢拔出，振捣棒头应插入下层混凝土5～10cm",false,{"key":20,"text":21,"correct":18},"C","严禁振捣器直接碰撞模板、钢筋及预埋件",{"key":23,"text":24,"correct":18},"D","混凝土浇筑过程中，严禁在仓内加水","混凝土浇筑振捣应遵守下列规定： ①混凝土浇筑应先平仓后振捣，严禁以振捣代替平仓。振捣时间以混凝土粗骨料不再显著下沉，并开始泛浆为准，应避免欠振、过振或漏振。 ②振捣棒组应垂直插入混凝土中，如略有倾斜，则倾斜方向应保持一致，以免漏振，振捣完应慢慢拔出，振捣棒头应插入下层混凝土5～10cm。 ③严禁振捣器直接碰撞模板、钢筋及预埋件。 ④混凝土浇筑过程中，严禁在仓内加水，混凝土和易性较差时，必须采取加强振捣等措施；仓内的泌水必须及时排除；应避免外来水进入仓内，严禁在模板上开孔赶水，带走灰浆；应随时清除黏附在模板、钢筋和预埋件表面的砂浆；应有专人做好模板维护，防止模板位移、变形。 ⑤在预埋件特别是止水片、止浆片周围，应细心振捣，必要时辅以人工捣固密实。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]