[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106427":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106427,782,1,"单选题","一期、二期埋件的埋设位置、临时支撑、加固措施、埋设公差经（ ）自检合格后，在混凝土浇筑之前应通知监理工程师检查签证。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","安装单位",true,{"key":16,"text":17,"correct":18},"B","设计单位",false,{"key":20,"text":21,"correct":18},"C","建设单位",{"key":23,"text":24,"correct":18},"D","施工单位","埋件安装后混凝土浇筑之前的检查签证：一期、二期埋件的埋设位置、临时支撑、加固措施、埋设公差经安装单位自检合格后。在混凝土浇筑之前应通知监理工程师检查签证。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]