[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106426":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106426,782,1,"单选题","埋件的二期混凝土强度达到（ ）以后方可拆模。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","30%",false,{"key":16,"text":17,"correct":14},"B","50%",{"key":19,"text":20,"correct":21},"C","70%",true,{"key":23,"text":24,"correct":14},"D","100%","埋件的二期混凝土强度达到70%以后方可拆模，拆模后应对埋件进行复测，并做好记录。同时检查混凝土尺寸，清除遗留的外漏钢筋头和模板等杂物，以免影响闸门启闭。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]