[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106421":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106421,782,1,"单选题","以下关于有负荷调试必须具备条件的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","无负荷调试中发现的各类质量问题部分已解决完毕",true,{"key":16,"text":17,"correct":18},"B","工程的全部辅助生产系统满足调试需要并畅通无阻",false,{"key":20,"text":21,"correct":18},"C","生产操作人员配备齐全，辅助材料准备妥当",{"key":23,"text":24,"correct":18},"D","对生产的处理量、产量、产品品种及其质量等是否达到设计要求，进行全面检验和评价","进行有负荷调试必须具备以下条件：无负荷调试中发现的各类质量问题均已解决完毕，工程的全部辅助生产系统满足调试需要并畅通无阻，公用工程配套齐全；生产操作人员配备齐全，辅助材料准备妥当，相应的生产管理制度建立齐全，通过有负荷调试，以进一步发现工程的质量问题，并对生产的处理量、产量、产品品种及其质量等是否达到设计要求，进行全面检验和评价。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]