[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106418":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106418,782,1,"单选题","开工准备时，监理机构的准备工作不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","依据监理合同约定，进场后及时设立监理机构",false,{"key":16,"text":17,"correct":18},"B","提请承包人提供工程设计及批复文件",true,{"key":20,"text":21,"correct":14},"C","组织编制监理规划",{"key":23,"text":24,"correct":14},"D","依据监理规划和工程进展，结合批准的施工措施计划，及时编制监理实施细则","监理机构的准备工作：①依据监理合同约定，进场后及时设立监理机构，配置监理人员，并进行必要的岗前培训。②建立监理工作制度。③提请发包人提供工程设计及批复文件、合同文件及相关资料。收集并熟悉工程建设法律、法规、规章和技术标准等。④依据监理合同约定接收由发包人提供的交通、通信、办公设施和食宿条件等，完善办公和生活条件。⑤组织编制监理规划，在约定的期限内报送发包人。⑥依据监理规划和工程进展，结合批准的施工措施计划，及时编制监理实施细则。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]