[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106417":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106417,782,1,"单选题","监理机构在对承包人的施工组织设计和技术措施进行仔细审查后提出意见和建议，并用（ ）答复承包人是否批准施工组织设计和技术措施。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","口头形式",false,{"key":16,"text":17,"correct":14},"B","口头或者书面形式",{"key":19,"text":20,"correct":21},"C","书面形式",true,{"key":23,"text":24,"correct":14},"D","口头之后，追加书面形式","监理机构在对承包人的施工组织设计和技术措施进行仔细审查后提出意见和建议，并用书面形式答复承包人是否批准施工组织设计和技术措施，是否需要修改。如果需要修改，承包人应对施工组织设计和技术措施进行修改后提出新的施工组织设计和技术措施，再次提请监理机构审查，直至批准为止。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]