[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106416":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1106416,782,1,"单选题","关于工程隐蔽部位覆盖前检查的说法，错误的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","监理机构应加强重要隐蔽单元工程和关键部位单元工程的质量控制",false,{"key":16,"text":17,"correct":14},"B","经承包人自检确认的工程隐蔽部位具备覆盖条件后，承包人应通知监理机构在约定的期限内检查",{"key":19,"text":20,"correct":21},"C","监理机构未按约定的时间进行检查的，承包人不可自行完成覆盖工作",true,{"key":23,"text":24,"correct":14},"D","承包人覆盖工程隐蔽部位后，监理机构对质量有疑问的，可要求承包人对已覆盖的部位进行钻孔探测或揭开重新检验","监理机构未按约定的时间进行检查的，除监理机构另有指示外，承包人可自行完成覆盖工作，并作相应记录报送监理机构，监理机构应签字确认。监理机构事后对检查记录有疑问的，可进行重新检查。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]