[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106409":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1106409,782,1,"单选题","工程建设项目招标的三个阶段工作不包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","招标结束阶段",true,{"key":16,"text":17,"correct":18},"B","招标准备阶段",false,{"key":20,"text":21,"correct":18},"C","招标阶段",{"key":23,"text":24,"correct":18},"D","决标阶段","工程建设项目招标过程可分为三个阶段工作：①招标准备阶段。从办理申请招标开始，到发出招标公告或邀请招标时发出投标邀请函为止；②招标阶段。从发布公告之日起，到投标截止之日止；③决标阶段。从开标之日起，到与中标单位签订承包合同为止。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]