[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1106398":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1106398,782,1,"单选题","我国目前的设计阶段可以分为初步设计阶段和（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","具体设计阶段",false,{"key":16,"text":17,"correct":18},"B","施工图设计阶段",true,{"key":20,"text":21,"correct":14},"C","二次设计阶段",{"key":23,"text":24,"correct":14},"D","水文地质勘察阶段","我国目前的设计阶段可以分为两个阶段，即初步设计阶段和施工图设计阶段。设计内容包括：初步设计、工程概算，施工图设计、工程预算。对于一些复杂的，采用新工艺、新技术的项目，可以在初步设计之后增加技术设计阶段。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（水利工程）","建筑工程",0]